Shah Jignesh Crack Aptitude Test
1200 men can construct a wall of length 1500metres in 30days. In how many days can half the previous strength construct 1800 metres of wall working 1/3 rd more time per day than in the previos case
Like · Comment ·

Konik Pokar

1) If 1200 Men Construct Whole 1800m Wall By Takinh 1/3rd more Time Per Day Then Previous Case Then It Will Take Time Of 27 Day To Construct 1800m Wall
Like ·

Konik Pokar

2) If 1200 Men Construt 300m Wall Of 1800m (1500m Wall Constructed Previously) Then It Will Take Time Of 4.5 Day More To Construct 300m Wall Total Wall 1500 + 300 = 1800 And Total Time Taken Is 30 + 4.5 = 34.5 Days
Like ·

Jay Kamdar

6 day more than previous case.. (36 days)...
Like ·

Anjul Meid

54 days is the answer
Like ·